Pool Shutdown Progress: 

Week 5 Update

October 7, 2025
 

The Aquatic and Facility Maintenance team continues to make great progress during week 5 of the pool shutdown. 

Here's a look at what was completed or is underway this week: 

  • Installed five (5) new toilets
  • Disinfected garbage bins
  • Cleaned and organized the WIBIT obstacle and storage room
  • Disinfected deck walls
  • Replaced the deck shower light
  • Continued tile work around the deck
  • Cleaned and organized the spray park, mechanical, and storage room

Thank you for your continued patience and support as we work towards reopening a refreshed, clean, and well-maintained aquatic space for everyone to enjoy.  

Remember, all other rec centre amenities remain open, including the bouldering wall, arenas and courts, so come on down to enjoy some indoor recreation.

Pool Shutdown
Share on Facebook
Share on Twitter
Share via Email

Copyright © 2025 Town of Hinton. All Rights Reserved.
131 Civic Centre Rd Hinton, AB T7V 2E5

Powered by
CivicSend - A product of CivicPlus